Project overview
Over a four-month period, our team successfully supported the Transnet Ore Line Shutdown by supplying ballast materials across multiple operational sections. The scope of work covered key segments between Sishen Yard in Saldanha to Loop 19, contributing directly to track maintenance, screening, and rehabilitation activities. The project formed part of a broader infrastructure programme focused on improving track stability, operational efficiency, and long-term reliability across the corridor.
Ballast delivered
Total ballast supplied (m³)
- 51 531.89 m³ (Tygerberg Quarry, Peak Quarry)
- 45 942.98 m³ (Lyttleton Dolomite, Glen Douglas Dolomite and Coega Quarry)
- Total ballast-related track length: 861km
Scope of work supported
The ballast supplied was used across several key activities, including:
- Ballast screening operations across multiple loops
- Ballast replenishment in critical sections
- Track maintenance and stabilisation
- Support to sleeper replacement programmes and general track upgrades
These activities are essential to maintaining track geometry, drainage, and load-bearing performance under heavy haul conditions.
This achievement reflects our team’s ability to deliver at scale under demanding shutdown conditions, supporting one of the country’s most critical freight corridors. The successful execution underscores our commitment to operational excellence and partnership with Transnet. Duration of the project (Phase 1 – Due date was 10 May, Phase 2 Due Date October 2026).